I had the same problem when I tried to deploy the WAR file on my Red Hat Jboss EAP 7.0.

But the server was integrated into my IDE (Eclipse Neon) and the problem only occured in Debug-Modus.

I was able to solve the problem by removing all breakpoints and after that i started the server again.

Try increasing timeout by adding java option "blocking.timeout". You can do it in bin/standalone.conf.bat (depends on how you configure wildfly) by adding line:
set "JAVA_OPTS=%JAVA_OPTS% -Djboss.as.management.blocking.timeout=600
Change the number if it's not enough.

increasing the timeout doesn't solve the root cause of the problem. You need to check the cause of the time of the block and solve the issue. Maybe in some cases the solution is to increase the timeout.

In most cases, increasing resources is a bad way to solve issues. I had this case, the Wildfly took a lot of time to boot. I increased the timeout to 600 and solved the issue but was still having issue with the wildfly booting time which was so annoying.

2018-03-26 07:50:36,523 ERROR [org.jboss.as.controller.management-operation] (Controller Boot Thread) WFLYCTL0348: Timeout after [300] seconds waiting for service container stability. Operation will roll back. Step that first updated the service container was 'add' at address '[("path" => "xxxxxxxxxxxxxxxx")]'

Finally I checked the block cause in and found the block was due to network host resolving (NAS storage defined as a path in wildfly).

I jumped to the network setting and found that my local DNS was not set properly. I added the local DNS instead of the public DNS and the block issue was gone. Hope this helps

Regards Sleem

user7072197

When i tried to debug and started the server with debug mode got the following error:

16:19:50,096 ERROR [org.jboss.as.controller.management-operation] (management-handler-thread - 1) JBAS013412: Timeout after [300] seconds waiting for service container stability. Operation will roll back. Step that first updated the service container was 'deploy' at address '[("deployment" => "ViprWeb.war")]'
16:19:50,096 ERROR [org.jboss.as.server] (management-handler-thread - 1) JBAS015870
16:20:00,117 ERROR [org.jboss.as.controller.management-operation] (management-handler-thread - 1) JBAS013413: Timeout after [5000] seconds waiting for service container stability while finalizing an operation.

I removed all my breakpoints and restarted my server jboss and it resolved the issue.

just increase time out in standalone.conf.bat set as set "JAVA_OPTS=%JAVA_OPTS% -Djboss.as.management.blocking.timeout=600 It worked for me.

Same problem, with netbeans

but I had not break points. Running jboss by command line, helped me

  • Stop jboss
  • Close Netbeans
  • open command line
  • Go to jboss folder > bin >
  • type: standalone.bat (this starts jboss)
  • open Netbeans
  • worked fine!

    Hope it'll help someone else.
Alexander Lu

I had the same problem. Then I killed the Kaspersky process and it helped!

I tackled a similar problem and had only succeed with undeploy the the apps. This gave a clean environment for Wildfly to restart and start the management and http-service. Then deploy the apps/WARs and identify what got you to this state.

In my case it was transactions that wanted to recover and deleting those from DB solve the problem bot to re-occur.