How to deliver a baseline from one project to another project in UCM?

后端 未结 1 347
一生所求
一生所求 2020-12-20 03:50

I am having 2 projects in clearcase UCM as follows

Project-200
Project-200.1

In Project-200.1 , We have completed a work and applied a base

相关标签:
1条回答
  • 2020-12-20 04:18

    You simply make an inter-project deliver of your baseline.
    As long as both projects have the same component, and if the deliver policy of the destination project authorize inter-delivers, you can initiate it between a stream of Project-200.1 and a Stream of Project-200.

    deliver policies

    For specifying a target Stream which is different from the default one (ie different from its immediate parent Stream), you need to initiate a "deliver to alternate target".

    0 讨论(0)