I\'ve been wondering if there are known solutions for algorithm of creating a school timetable. Basically, it\'s about optimizing \"hour-dispersion\" (both in teachers and
This problem is NP-Complete!
In a nutshell one needs to explore all possible combinations to find the list of acceptable solutions. Because of the variations in the circumstances in which the problem appears at various schools (for example: Are there constraints with regards to classrooms?, Are some of the classes split in sub-groups some of the time?, Is this a weekly schedule? etc.) there isn't a well known problem class which corresponds to all the scheduling problems. Maybe, the Knapsack problem has many elements of similarity with these problems at large.
A confirmation that this is both a hard problem and one for which people perennially seek a solution, is to check this (long) list of (mostly commercial) software scheduling tools
Because of the big number of variables involved, the biggest source of which are, typically, the faculty member's desires ;-)..., it is typically impractical to consider enumerating all possible combinations. Instead we need to choose an approach which visits a subset of the problem/solution spaces.
- Genetic Algorithms, cited in another answer is (or, IMHO, seems) well equipped to perform this kind of semi-guided search (The problem being to find a good evaluation function for the candidates to be kept for the next generation)
- Graph Rewriting approaches are also of use with this type of combinatorial optimization problems.
Rather than focusing on particular implementations of an automatic schedule generator program, I'd like to suggest a few strategies which can be applied, at the level of the definition of the problem.
The general rationale is that in most real world scheduling problems, some compromises will be required, not all constraints, expressed and implied: will be satisfied fully. Therefore we help ourselves by:
In proof-reading this answer , I realize it is quite shy of providing a definite response, but it none the less full of practical suggestions. I hope this help, with what is, after all, a "hard problem".
Here are a few links I found:
School timetable - Lists some problems involved
A Hybrid Genetic Algorithm for School Timetabling
Scheduling Utilities and Tools
UPDATE: from comments ... should have heuristics too!
I'd go with Prolog ... then use Ruby or Perl or something to cleanup your solution into a prettier form.
teaches(Jill,math).
teaches(Joe,history).
involves(MA101,math).
involves(SS104,history).
myHeuristic(D,A,B) :- [test_case]->D='<';D='>'.
createSchedule :- findall(Class,involves(Class,Subject),Classes),
predsort(myHeuristic,Classes,ClassesNew),
createSchedule(ClassesNew,[]).
createSchedule(Classes,Scheduled) :- [the actual recursive algorithm].
I am (still) in the process of doing something similar to this problem but using the same path as I just mentioned. Prolog (as a functional language) really makes solving NP-Hard problems easier.
My timetabling algorithm, implemented in FET (Free Timetabling Software, http://lalescu.ro/liviu/fet/ , a successful application):
The algorithm is heuristic. I named it "recursive swapping".
Input: a set of activities A_1...A_n and the constraints.
Output: a set of times TA_1...TA_n (the time slot of each activity. Rooms are excluded here, for simplicity). The algorithm must put each activity at a time slot, respecting constraints. Each TA_i is between 0 (T_1) and max_time_slots-1 (T_m).
Constraints:
C1) Basic: a list of pairs of activities which cannot be simultaneous (for instance, A_1 and A_2, because they have the same teacher or the same students);
C2) Lots of other constraints (excluded here, for simplicity).
The timetabling algorithm (which I named "recursive swapping"):
Try to place each activity (A_i) in an allowed time slot, following the above order, one at a time. Search for an available slot (T_j) for A_i, in which this activity can be placed respecting the constraints. If more slots are available, choose a random one. If none is available, do recursive swapping:
a. For each time slot T_j, consider what happens if you put A_i into T_j. There will be a list of other activities which don't agree with this move (for instance, activity A_k is on the same slot T_j and has the same teacher or same students as A_i). Keep a list of conflicting activities for each time slot T_j.
b. Choose a slot (T_j) with lowest number of conflicting activities. Say the list of activities in this slot contains 3 activities: A_p, A_q, A_r.
c. Place A_i at T_j and make A_p, A_q, A_r unallocated.
d. Recursively try to place A_p, A_q, A_r (if the level of recursion is not too large, say 14, and if the total number of recursive calls counted since step 2) on A_i began is not too large, say 2*n), as in step 2).
e. If successfully placed A_p, A_q, A_r, return with success, otherwise try other time slots (go to step 2 b) and choose the next best time slot).
f. If all (or a reasonable number of) time slots were tried unsuccessfully, return without success.
g. If we are at level 0, and we had no success in placing A_i, place it like in steps 2 b) and 2 c), but without recursion. We have now 3 - 1 = 2 more activities to place. Go to step 2) (some methods to avoid cycling are used here).
Generally, constraint programming is a good approach to this type of scheduling problem. A search on "constraint programming" and scheduling or "constraint based scheduling" both within stack overflow and on Google will generate some good references. It's not impossible - it's just a little hard to think about when using traditional optimization methods like linear or integer optimization. One output would be - does a schedule exist that satisfies all the requirements? That, in itself, is obviously helpful.
Good luck !
It's a mess. a royal mess. To add to the answers, already very complete, I want to point out my family experience. My mother was a teacher and used to be involved in the process.
Turns out that having a computer to do so is not only difficult to code per-se, it is also difficult because there are conditions that are difficult to specify to a pre-baked computer program. Examples:
As you can see, the problem is not NP-complete, it's NP-insane.
So what they do is that they have a large table with small plastic insets, and they move the insets around until a satisfying result is obtained. They never start from scratch: they normally start from the previous year timetable and make adjustments.