YARN Application Master unable to connect to Resource Manager

前端 未结 3 713

I have a 4 node cluster (1 Namenode/Resource Manager 3 datanodes/node managers)

I am trying to run a simple tez example orderedWordCount

hadoop jar          


        
3条回答
  •  陌清茗
    陌清茗 (楼主)
    2021-01-05 09:46

    It is because your resource manager is not reachable. Try to ping you resource manager from other nodes and see if it works. Maintain these configs consistent across cluster.