In SQL Server 2008 the isoweek can be found with this:

SELECT datepart(iso_week, getdate())

Before SQL Server 2008 there were no built-in f

4条回答
  •  天涯浪人
    2020-11-29 08:17

    There is a link here for other earlier attempts http://www.sqlteam.com/forums/topic.asp?TOPIC_ID=60510

    This is the OLD code for the function

    CREATE function f_isoweek(@date datetime)
    RETURNS INT
    as
    BEGIN
    DECLARE @rv int
    
    SELECT @rv = datediff(ww, dateadd(ww, datediff(d, 0, dateadd(yy, datediff(yy, 0, day4),3))/7,-4),day4)
    FROM (SELECT dateadd(ww, datediff(day, 0, @date)/7, 3) day4) a
    
    RETURN @rv
    END
    

    After combining @AndriyM 's brilliant answer with my own, we are down to 1 line. This is the NEW code.

    CREATE function f_isoweek(@date datetime)
    RETURNS INT
    as
    BEGIN
    
    RETURN (datepart(DY, datediff(d, 0, @date) / 7 * 7 + 3)+6) / 7
    -- replaced code for yet another improvement.
    --RETURN (datepart(DY, dateadd(ww, datediff(d, 0, @date) / 7, 3))+6) / 7
    
    END
    

    Explanation for the old code (not going to explain the new code. It is fragments from my code and AndriyM's code):

    Finding weekday 4 of the chosen date

    dateadd(week, datediff(day, 0, @date)/7, 3) 
    

    Finding isoyear - year of weekday 4 of a week is always the same year as the isoyear of that week

    datediff(yy, 0, day4)
    

    When adding 3 days to the first day of the isoyear a random day of the first isoweek of the isoyear is found

    dateadd(yy, datediff(yy, 0, day4),3)
    

    finding relative week of the first isoweek of the isoyear

    datediff(d, 0, dateadd(yy, datediff(yy, 0, day4),3))/7
    

    Finding the monday minus 4 days of the first isoweek results in thursday of the week BEFORE the first day of the first isoweek of the isoyear

    dateadd(ww, datediff(d, 0, dateadd(yy, datediff(yy, 0, day4),3))/7,-4)
    

    Knowing first thursday of the week before the first isoweek and first thursday of the chosen week, makes it is quite easy to calculate the week, it doesn't matter which setting datefirst has since the weekdays of both dates are thursdays.

    datediff(ww, dateadd(ww, datediff(d, 0, dateadd(yy, datediff(yy, 0, day4),3))/7,-4),day4)
    