How to deliver a baseline from one project to another project in UCM?

霸气de小男生 提交于 2019-11-29 12:04:37

You simply make an inter-project deliver of your baseline.
As long as both projects have the same component, and if the deliver policy of the destination project authorize inter-delivers, you can initiate it between a stream of Project-200.1 and a Stream of Project-200.

For specifying a target Stream which is different from the default one (ie different from its immediate parent Stream), you need to initiate a "deliver to alternate target".