How to deliver a baseline from one project to another project in UCM?

南楼画角 提交于 2019-11-28 05:45:50

问题


I am having 2 projects in clearcase UCM as follows

Project-200
Project-200.1

In Project-200.1 , We have completed a work and applied a baseline

"Project-200.1-1.1.0.0"

Now we would like to deliver from Project-200.1 to Project-200.

How to deliver the baselined contents? We do not want to deliver any thing which is added after baseline.


回答1:


You simply make an inter-project deliver of your baseline.
As long as both projects have the same component, and if the deliver policy of the destination project authorize inter-delivers, you can initiate it between a stream of Project-200.1 and a Stream of Project-200.

For specifying a target Stream which is different from the default one (ie different from its immediate parent Stream), you need to initiate a "deliver to alternate target".



来源:https://stackoverflow.com/questions/10005364/how-to-deliver-a-baseline-from-one-project-to-another-project-in-ucm

易学教程内所有资源均来自网络或用户发布的内容,如有违反法律规定的内容欢迎反馈
该文章没有解决你所遇到的问题?点击提问,说说你的问题,让更多的人一起探讨吧!